Advisory

When the rule is applied before its parameters are published

The 2026 figures will be calculated under a methodology whose parameters have not yet been published, and 2026 falls within the five-year window used to calculate 2027 firm capacity. What is decided in October will not be corrected in November.

EnergySage

Combined-cycle power plant on the northern coast, at blue hour

In the Chilean power market, the rule changes that have worked share two conditions: they went through the right channel, with the parameters on the table.

In the Diesel Fuel Availability Uncertainty Factor procedure, the second condition is still pending — and the timing makes that sequence matter well beyond diesel.

The technical diagnosis is correct

Worth starting there, because the debate is not about the diagnosis: a unit that is technically available but lacks the fuel to sustain its output is not real backup. ACERA, the renewables trade association, quantified it — on the order of 3,500 m³/day of replenishment capacity against the ~25,000 m³/day that running the full fleet at full load would require.

That gap is real and deserves a methodology that recognizes it. The debate is not whether the gap exists.

The issue is sequencing

On July 31 The CEN, Chile’s independent system operator (ISO), extended the comment period. Companies had asked for until August 21; they got a week.

Alongside the extension, something else had been requested: publishing a worked example of how the factor would be applied, along with the supporting material for the Diesel Report. That did not happen. The replenishment zones and their capacity remain undefined — deferred to a later technical study.

The result is that additional days were granted to analyze something that still is not calculable. No company can estimate its exposure without the zones or that worked example. The extension addressed the form of the request; the substance is still pending.

Why the schedule matters more than the deadline

The methodology enters the initial capacity (Pini) calculation, with first application in October. From there it flows into the five-year window behind 2027’s firm capacity.

That means 2026 will be calculated under a methodology whose parameters have yet to be published. And a year that enters a five-year window does not get corrected afterward: what is decided in October is not amended in November. It carries for five years.

The process, moreover, is far from closed even after the comment period closes: the replenishment zones are still missing, as are verification of the contractual taxonomy against real portfolios, the first application, and the carry-through to the five-year window.

What can be done without the worked example

There is a practical difference between waiting for that worked example and sizing one’s own exposure using the mechanics already published. The latter is possible today, and it is what makes it possible to enter the conversation with a number rather than a procedural objection.

That, concretely, is the distance between following a regulatory process and anticipating its effect on one’s own revenue.

The implications go beyond diesel

If an internal procedure can redefine the capacity revenue base of a technology without publishing the parameters that determine it, the same mechanism can apply to storage tomorrow.

At that point it is no longer about amortized assets, but about the pipeline currently being financed — where a shift in the capacity revenue base does not just adjust a margin: it decides whether the project closes.

How to cite this analysis

EnergySage (2026). "When the rule is applied before its parameters are published". Published Aug 7, 2026. https://energysage.cl/en/analisis/potencia-suficiencia-parametros-sin-publicar/

Plain-text version (Markdown)

Talk to us

Our first conversation focuses on understanding your situation.

Email us at

[email protected]

Open in Gmail Open in Outlook